Concrete pour tomorrow (Monday 17 October). The delay was that Thursday 6 October the tractor digging the drive-way level, found the mains water pipe kinked on the Council side of the water metre.

Council workers came out Monday 10 October and that put back the sand truck to Wednesday 12 October which in turn put back the availability of the concrete truck to Monday 17 October.

Two days to cure - Tuesday 18th and Wednesday 19th - then we leave for Timeout in the Tweed on Thursday 20 October. Never mind. Notice the width of the drive way, the full size of the large double gate. It's this wide in order that missionaries are on concrete in the wet season all the way to the house steps.